Project Status
Licensing & Approvals:
-
Survey License
Obtained on 2073-02-20, renewed in 2075-02-20.
-
PPA (Power Purchase Agreement)
Signed with NEA for 7.25 MW on 29th Bhadra 2074.
-
COD
2081/01/06
-
Generation License
Obtained on 2076-05-26.
-
Financial Closure
Syndicated loan agreement signed on 2077-07-04 with Kumari Bank Ltd. and Shangrila Development Bank.
Design & Engineering:
-
Feasibility Report
Prepared in Ashad 2073.
-
Detailed Engineering Design Report
Prepared in Ashwin 2076.
Environmental & Social Aspects
-
EIA Report
Approved on 2076-03-20.
-
Land Acquisition
Private Land: 24 Ropani purchased, 8.98 Ropani Compensated to Government
-
Tree Cutting
357 trees cut as per government approval along with compensation plantation work completed at 1:25 ratio
-
Environmental Mitigation
Implementing environmental plans as per the approved EIA.
Infrastructure Development
-
Access Road
Constructed 4 km road from Bhujung Village to Powerhouse.
-
Project Road (Headworks to Powerhouse)
4.1 km road constructed
-
Site Camp
Permanent camp blocks constructed
IPO Process
-
Applied for IPO
listed in SEBON ,pipeline priority no 4
-
Numbers of Share Planned for Public
20,00,000 nos