Project Status

Licensing & Approvals:

  • Survey License

    Obtained on 2073-02-20, renewed in 2075-02-20.

  • PPA (Power Purchase Agreement)

    Signed with NEA for 7.25 MW on 29th Bhadra 2074.

  • COD

    2081/01/06

  • Generation License

    Obtained on 2076-05-26.

  • Financial Closure

    Syndicated loan agreement signed on 2077-07-04 with Kumari Bank Ltd. and Shangrila Development Bank.

Design & Engineering:

  • Feasibility Report

    Prepared in Ashad 2073.

  • Detailed Engineering Design Report

    Prepared in Ashwin 2076.

Environmental & Social Aspects

  • EIA Report

    Approved on 2076-03-20.

  • Land Acquisition

    Private Land: 24 Ropani purchased, 8.98 Ropani Compensated to Government

  • Tree Cutting

    357 trees cut as per government approval along with compensation plantation work completed at 1:25 ratio

  • Environmental Mitigation

    Implementing environmental plans as per the approved EIA.

Infrastructure Development

  • Access Road

    Constructed 4 km road from Bhujung Village to Powerhouse.

  • Project Road (Headworks to Powerhouse)

    4.1 km road constructed

  • Site Camp

    Permanent camp blocks constructed

IPO Process

  • Applied for IPO

    listed in SEBON ,pipeline priority no 4

  • Numbers of Share Planned for Public

    20,00,000 nos